“In The Know” – June 2020

Casa Del Mar HOA President’s  “In the Know” for June 2020

(IF YOU HAVE A TENANT, PLEASE FORWARD THIS INFORMATION)

  1. Building maintenance:  First phase of maintenance complete. Second phase to begin approx. 29 June.  Below is from the contractors notes.  A bit mixed up as you can see but the main message is to have your unit ready by having access to all walls. They must be able to gain access to all outside portions of your unit!  It’s about 2-3 weeks of work. Be ready. If you need someone to check your unit contact me per below contact information.  If you don’t see your unit below it may be good to go.  If you know of something not on this list contact me to add to the repairs.  As  the contractor is working and he sees something not noted it will be fixed.  We have tried to see all damage but there may be some items we missed. 

Unit 501 Trim at corner of garage West wall window trim 1- 4’x 8’ T-111 siding Belly band trim Fascia at corner of garage Window trim at garage 2nd Story window trim @ garage

Unit 503 Chimney trim Fascia at garage corner 2nd Story fascia corner Siding above garage

Unit 505 Chimney trim and fascia Garage corner fascia

Unit 507 Garage corner fascia Garage window trim

Unit 509 Garage corner fascia East wall window trim x 3 Siding trim Corner 2nd story fascia

Unit 515 Roof sheathing above the electrical panel Siding above electrical panel 2nd Story window trim 2nd Story window trim north wall Siding and trim at the base of chimney

Unit 517 Remove 2nd story trim  at the slider and chimney x2

Unit 519 Rear yard siding and trim at slider

Unit 521 Trim and fascia at entry 1st level 2nd level trim a garage corner Garage door trim

Unit 525 Rear trim and chimney siding Upstairs front window trim

Unit 527 Rear fascia

Unit 529 Back side of chimney siding Rear fascia at patio Sheathing 2nd level above entry Fascia at 1st level entry Fascia at garage corner

Unit 531 Garage corner fascia and secondary fascia

Unit 533 Siding below electrical panel repair 2nd fascia at garage corner Rear window trim Fascia above slider 2nd Story fascia and trim at rear

Unit 535 Fascia at entry Rear chimney trim

Unit 541 Cut trim at chimney base Fascia at entry

Unit 545 Trim at slider Siding at base next to slider Fascia above slider Trim at base of chimney Check flashing at chimney Check the chimney stack

Unit 551 Corner fascia 2nd story window trim gable wall Fascia at entry by electrical panel 2 siding epoxy repairs 2nd Story window trim at entry

Unit 553 Repaint repairs Paint chimney trim

Unit 555 2nd Story fascia above splice and Chimney flashing

Unit 559 Garage window trim 1”x4” belly band top and bottom Roof sheathing and fascia at the rear West side window trim Roof sheathing “spongy” remove shingles and replace sheathing re roof after the repair

Unit 534 Fascia at the garage Siding at entry above the plant

Unit 530 Trim at corner of garage base

Unit 526 Remove satellite dish Window trim at the north side

2.  A reminder about Satellite dishes:  All dishes not in use should be removed. Contact me for help if you or the dish company cannot remove.  Did you know the local cable company, San Simeon Cable and Internet, can provide service to your unit?  (805-927-5555).   

3.  Driveway:  We are working on a date for asphalt to be removed and replaced with pavers. 

4.  Bird Nesting:  The nesting problem has been resolved for this season.  Next year could be an issue.  We’ll have to wait to see if they return.  

5.  Chimneys:  Working on the contract to have chimneys repaired as some caps, etc. need attention.

Thanks for your support and patience!

V/r, Tom Kiel 

Casa Del Mar HOA President

Leave a Reply